Tilbury Douglas Tilbury Douglas
  • About
    • About us
    • Digital
    • ESG
    • Financial updates
    • Health, safety and wellbeing
    • History
    • Inclusive procurement
    • Leadership team
    • Policies, reports and certificates
    • Supply chain
  • Sectors
    • Central and local government
    • Defence
    • Devolved government
    • Education
    • Health
    • Justice
    • Water
  • Services
    • Regional Building
    • Fit-Out
    • Engineering
    • Infrastructure
  • Projects
  • Frameworks
  • News & media
    • Press releases
    • Insight articles
    • Videos
  • Careers
    • Overview
    • Current vacancies
    • Early careers
    • Women in construction
  • Contact
    • Contact details
    • Office locations

Bankhead Depot

  • Location: Edinburgh
  • Sector: Industrial
  • Service: Regional Building

Tilbury Douglas delivered the remodelling of Bankhead Depot for the City of Edinburgh Council, transforming the live facility to better support the Council’s Roads Department.

Key stats

Located within a busy industrial estate, the depot comprises offices, stores, workshops, a salt store and operational road maintenance vehicles and equipment. The project repurposed the main workshop buildings to create a bespoke vehicle maintenance garage and a new blacksmiths workshop, supported by modern office and welfare accommodation.

New servicing infrastructure, utilities and yard facilities were also installed across the site. As the depot remained fully operational, the works were carefully phased around essential road maintenance activities, with close end user collaboration minimising downtime and disruption. The completed project provides improved, purpose designed facilities while supporting the continued delivery of essential services across Edinburgh.

The project involved extensive alterations to the depot’s main workshop buildings, converting them into a bespoke garage for maintaining City of Edinburgh Council vehicles and a new blacksmiths workshop with associated offices and welfare facilities. Bespoke metal maintenance pits were installed within the garage areas, requiring significant excavation, temporary works and civil engineering. An under chassis vehicle wash system was constructed in the centre of the operational yard.

Extensive trenching enabled new power and gas services to be installed throughout the site, increasing supply capacity across the facility. The existing overhead gantry crane was relocated to the new blacksmiths workshop, together with new supporting steelwork and services. Existing workshop equipment was also transferred and reused. The works were divided into phases, allowing the depot, workshops, stores and road-maintenance operations to remain functional throughout construction.

At a glance...

£3.6m

Project value

November 2023

Completion date

City of Edinburgh Council

Customer

Innovation and technical excellence

Tilbury Douglas’ in house temporary works team assessed the ground conditions around the new bespoke maintenance pits and developed a solution that minimised the extent of excavation required. This reduced disruption within the operational depot and lowered the health and safety risks associated with deep excavations. Detailed planning also enabled the existing overhead gantry crane and workshop equipment to be relocated and reused in the new blacksmiths facility, avoiding unnecessary replacement and limiting operational downtime.

Sustainability was supported through an initial survey that identified materials and site features suitable for retention. Excavated material was incorporated into the final design, reducing off site disposal, while just in time ordering limited damage and surplus materials. A Site Waste Management Plan forecast and monitored construction waste, with materials segregated to maximise recycling and returned to manufacturers through closed loop systems where possible.

Community and social impact

The project generated a 60% Social Value Return on Investment through a programme focused on education, employability and community wellbeing. Four pupils from Forrester High School completed on site work experience placements, while engagement with Developing the Young Workforce included skills days, employability sessions and site visits.

The team supported a careers fair at St Augustine’s High School and delivered construction talks at Edinburgh College and Wester Hailes High School. Mock interviews delivered with Jobcentre Plus helped local jobseekers develop practical skills and confidence.

Two local graduates were appointed as a Graduate Site Manager and Graduate Quantity Surveyor, while apprentices were supported across the project’s electrical and trade supply chain.

The team also volunteered with South East Edinburgh Foodbank and completed local litter picks, supporting vital services and improving the surrounding environment. Together, these initiatives created opportunities for local people and a positive legacy for Edinburgh.

Delivery and performance

Maintaining the City of Edinburgh Council’s road maintenance operations was central to the delivery strategy. Tilbury Douglas developed a detailed master programme that separated each phase into individual components and aligned the works with key operational dates. The new blacksmiths workshop was constructed beside the existing facility, which remained in use until equipment could be transferred to its new location.

Close collaboration with end users ensured the move was carefully sequenced and operational downtime kept to a minimum. Alterations to mechanical and electrical services within live areas were completed at agreed times to avoid disrupting depot activities. Work in the main yard, including extensive service trenching and installation of the vehicle wash system, was also phased around vehicle movements and essential access requirements. This structured approach enabled complex building, civil engineering and services works to progress safely while the busy depot remained operational.

Tilbury Douglas
Twitter LinkedIn YouTube

Trading address:
Oberon Road
Exeter Business Park
Exeter
EX1 3QD

0121 782 2727

  • Projects
  • Frameworks
  • Press releases
  • Modern slavery statement
  • Cookie policy
Build UK logo

Content © 2026 © 2026 Tilbury Douglas Construction Limited
Registered in England and Wales: 00303359 (Construction) and 03044398 (Engineering)
Registered office: 30 Eastcheap, London, EC3M 1HD. All rights reserved.

Powered by Greenhouse