North Lanarkshire Council Fleet Building
-
Location: Bellshill
-
Sector: Industrial
-
Service: Regional Building
Tilbury Douglas carried out the design and build of a new depot to service, maintain and MOT the North Lanarkshire Council (NLC) light goods and HGV vehicle fleet.
The facility replaced the existing buildings at Old Edinburgh Road in Bellshill which were no longer fit for purpose and were therefore demolished. NLC’s fleet of 670 vehicles and plant will be maintained at the site which has MOT facilities as well as stores, offices and welfare facilities for staff. The facility will also assist in the decarbonisation of the vehicles as the council moves forward with its net zero ambition.
The works comprised of the detailed design, construction and commissioning of a new Fleet Building which will house the North Lanarkshire Council Transportation team and their in house vehicle maintenance facilities. This facility will undertake routine maintenance on the NLC light goods and HGV fleet and will be a licenced MOT site with the DVSA.
The construction of a two-storey commercial / industrial depot took place within an existing NLC live site in Bellshill and included the following:
- Fleet vehicle servicing and MOT workshop
- Spare parts storage
- Open plan office
- Interview rooms
- Toilet accommodation
- Welfare accommodation incorporating showers, drying room, lockers and changing room
- Rest area
- Training area
- Toilet accommodation
At a glance...
£6m
Project value
January 2024
Completion date
North Lanarkshire Council
Customer
Innovation and technical excellence
The project team combined extensive experience across industrial, commercial, design and build, and live operational environments with a strong focus on value engineering and quality assurance. A review of the IPS and cubicle specification identified an alternative solution that reduced both cost and installation time without compromising product quality.
The team also reviewed the attenuation tank design, identifying an unnecessary membrane layer and proposing an alternative product that was less labour intensive to install, reduced programme time and cost, and provided greater storage capacity.
Quality was managed through a digital Quality Delivery Plan, which detailed construction record requirements, allocated ownership by trade and organised inspections by location in accordance with the agreed Inspection and Test Plan.
Witness and hold points were incorporated into the verification and sign off process, including checks of first and second fix mechanical and electrical installations. Together, these measures delivered efficiencies for the Customer while maintaining clear accountability, robust quality control and compliance with the specified requirements.
Community and social impact
With the project located close to several areas experiencing multiple deprivation, Tilbury Douglas developed a community benefits programme tailored to local needs. The project exceeded its agreed targets, delivering construction workshops, school visits, careers fairs and Women in Construction sessions. The team also built strong relationships with New College Lanarkshire, Bellshill Academy and St Andrew’s High School, while supporting Routes to Work and Jobcentre Plus through employability and toolbox-talk sessions.
Five local pupils gained practical work experience, and six new apprenticeships were created during the project. The team also maximised the project’s contribution to the local economy, with 81% of spend placed with local suppliers and 84% with SMEs. Together, these activities generated a 27% Social Value Return on Investment, leaving a positive legacy through skills development, employment opportunities and continued engagement with local schools and community organisations.
Delivery and performance
The building was delivered adjacent to North Lanarkshire Council’s operational fleet depot, where school buses and other fleet vehicles remained in daily use. Careful planning and coordination with the Council’s Transport Department maintained safe access and minimised disruption to employees, depot operations and neighbouring properties. Weekly meetings with Council staff allowed upcoming activities to be reviewed and managed around operational requirements.
The programme was affected when the Customer requested that utility connections take place later than originally planned, resulting in an extension of time. Tilbury Douglas supported the Customer by liaising daily with utility providers to accelerate the connections and limit further delay. The experience highlighted the importance of engaging utility providers at the earliest possible stage, particularly where industry resourcing pressures are increasing lead times. An experienced team with expertise in design and build and live environments maintained close control of safety, quality and coordination throughout delivery.