Waseley Hills High School
-
Location: Rednal
-
Sector: Education
-
Service: Regional Building
Tilbury Douglas was appointed to deliver the redevelopment of Waseley Hills High School on behalf of the Department for Education (DfE), creating a modern, net zero carbon secondary school for more than 1,000 pupils.
Delivered over three carefully planned phases on a live school campus, the project involved replacing ageing buildings with two new teaching blocks, specialist learning spaces and a dedicated Special Educational Needs department.
Having worked collaboratively with the DfE, school leadership and the local planning authority, the design was refined to enhance the campus layout, improve community access to sports facilities and create inspiring learning environments. Designed to DfE Spec 21 standards, the new school provides sustainable, modern educational facilities that support both academic achievement and long term community use.
The project comprised the phased demolition of the existing school buildings and construction of two new two storey teaching blocks while uninterrupted school operations were maintained throughout.
The new facilities included general and specialist classrooms, dining areas, Special Educational Needs provision, external landscaping and a Multi-Use Games Area (MUGA).
Delivered to DfE Spec 21 and net zero carbon standards, the development incorporated air source heat pumps, natural ventilation with heat recovery, thermal mass construction and 723 photovoltaic panels to create a fully electric campus, with gas retained only for specialist science laboratories. Extensive external works included new drainage infrastructure, hard landscaping and sustainable site improvements.
Careful decant planning, stakeholder coordination and phased handovers enabled teaching and learning to continue safely while construction progressed.
At a glance...
£34.5m
Project value
May 2027
Completion date
Department for Education
Customer
Innovation and technical excellence
Innovation was key to the delivery of Waseley Hills High School from the earliest design stages. Early contractor and supply chain involvement enabled thermal modelling, structural optimisation and coordinated mechanical and electrical (M&E) design to achieve the project’s ambitious net zero carbon objectives. The building integrated natural ventilation with heat recovery units, air source heat pumps, thermal mass and 723 photovoltaic panels to maximise operational efficiency.
Detailed ground investigations were undertaken during the pre construction period which informed a value engineered piled foundation solution, and improved programme certainty while reducing construction costs. The design was further enhanced through bespoke architectural features, which included a refined roof profile, upgraded façade treatments and specialist finishes within teaching spaces. Collaborative planning with the DfE and local authority also enabled the campus layout to be redesigned, improving safeguarding and creating dedicated community access to sports facilities without compromising operational efficiency.
Community and social impact
Creating lasting value for the local community was a key objective throughout the project. Construction activities were carefully planned to minimise disruption to Waseley Hills High School and neighbouring Hollywell Primary School, with delivery schedules aligned to avoid peak school traffic.
The project team delivered careers fairs, construction workshops and educational sessions with local pupils, helping to promote careers within the construction industry. Social value initiatives also included improvement works at Churchill Primary School and donations to a local food bank as part of Tilbury Douglas’ Winter Wishes campaign.
The completed development provides enhanced sports facilities designed to support community use outside school hours, extending the benefits beyond the school itself. The project’s commitment to responsible construction was recognised through the achievement of a perfect 45/45 Considerate Constructors Scheme score.
Delivery and performance
Delivering a major redevelopment on a live secondary school campus required meticulous planning, collaborative working and robust risk management. Tilbury Douglas developed a phased construction strategy that maintained uninterrupted teaching, safeguarded pupils and staff, and ensured safe access throughout the programme.
Early engagement with the client, design team and specialist supply chain reduced programme risk by resolving complex ground conditions, drainage requirements and electrical infrastructure before construction commenced. Sustainable construction practices, included on site reuse of demolition materials and extensive cut and fill operations, reduced waste and minimised environmental impact.
Careful logistical planning ensured construction traffic was managed around school opening and closing times to minimise disruption.
Our partners
-
M&E Engineer: Hoare Lea up to RIBA Stage 4 via David Pardine. Green and Webb via David Paradine from Stage 5
-
Structural Engineer: Nolans
-
Architect: Corstorphine and Wright
-
Framework: DfE Spec 21 Framework